Rufiji dam roads

Tanzania | Infrastructure | Infrastructure Design

Project Description

The civil works includes the following:
Permanent access roads connecting the site with the
existing roads networked length about 32km.
Temporary access roads that connect all permanent
facilities with length of 59km.
Value of Project: 45 Million USD

Project Details

CLIENT: Sweedy and Arab Contractors
LOCATION: Tanzania
PROJECT TYPE: Infrastructure
SCOPE OF WORK: Infrastructure Design

Scope of Work Details

Main dam for storage of water to generate hydro power using RCC concrete and a hydropower plant with a capacity of 2115mw and a substation of 400 kv, in addition to 400 kv transmission lines to the nearest point of the public network.